Second Giant Boring Machine Begins Work on Hudson Rail Tunnel

By Reuven1 min read ·

A second giant tunnel boring machine has begun excavating the new Hudson rail tunnel's southern tube, putting both tubes under construction in New Jersey, the Gateway Development Commission announced Wednesday.

The first machine began work on the northern tube in October. Together, the two machines are building the first 5,100 feet of the new tunnels, from North Bergen to an access shaft on the Weehawken-Hoboken border.

Once they reach that shaft, crews plan to remove them and use a different pair designed for the mixed ground beneath the Hudson River. This first section is expected to take about a year, including planned maintenance pauses.

Each machine excavates rock and installs concrete tunnel lining as it moves. Each will install nearly 850 rings assembled from more than 5,000 segments. The northern machine has already advanced about 400 feet and installed more than 60 rings, according to the commission.

The work is part of the $16 billion Hudson Tunnel Project. The milestone marks construction progress, not the opening of a new passenger tunnel.